A steel frame development located in central Slough.
​

DCD Ltd installed 8,500m² of metal decking, provided safety netting, and welded more than 14,000 19x95 (LAW) shear connectors as part of the works. For this contract, our mobile stud welding unit was deployed, providing a fully equipped on-site solution that ensured efficient delivery and flexibility around site logistics.

​

Delivered on a tight programme, the project required close coordination with the steel contractor to achieve safe and efficient installation in a busy town-centre environment.